About Veridue AI-powered due diligence and data rooms for renewables For investors and lenders: legal and technical red flag due diligence in 24 hours, every finding traced to its source document, and one place to screen projects and manage your pipeline. Your first diligence is on us. For developers: vendor due diligence in 24 hours, and a free AI-powered data room with automated expert Q&A, teaser generation and investment-readiness reports. Book a demo → |
Each week we track the regulatory changes across Europe that move a renewables project’s revenues, costs and timelines, from capture prices, balancing markets and auction rules to grid charges, connection queues and permitting.
It is written for investors, developers and independent power producers, their legal, technical, commercial and financial advisers, and anyone who wants to keep up with the biggest changes in European energy.
Read the takeaways for the week’s bigger themes, jump to the markets you follow, or spend a few minutes with our market deep dive. We cover the smaller changes too: the relevant update for your project may not be the biggest European headline.
This week’s takeaways
- Support schemes are adding conditions. France will limit Chinese magnets in its onshore wind tender, Flanders will withhold green certificates in negative-price hours, and Italy set out how bidders in its new renewables auctions qualify and post guarantees.
- More system services are opening to batteries. Hungary joined Europe’s shared balancing platforms, Great Britain’s National Energy System Operator (NESO) set rules for a reactive power market that pays at 0 MW, and Litgrid, Lithuania’s grid operator, is auctioning 154 MW of fast frequency response.
- Unused grid capacity is starting to cost money. Czechia will charge high-voltage customers for reserved capacity from January, and Finland’s Energy Authority confirmed terms that let grid companies take capacity back from projects that miss milestones. That is this week’s deep dive.
Find your market
🇪🇺 Across markets · 🇧🇪 Belgium · 🇭🇷 Croatia · 🇨🇿 Czechia · 🇩🇰 Denmark · 🇪🇪 Estonia · 🇫🇮 Finland · 🇫🇷 France · 🇬🇷 Greece · 🇭🇺 Hungary · 🇮🇪 Ireland · 🇮🇹 Italy · 🇱🇹 Lithuania · 🇳🇱 Netherlands · 🇳🇴 Norway · 🇷🇴 Romania · 🇪🇸 Spain · 🇸🇪 Sweden · 🇨🇭 Switzerland · 🇬🇧 United Kingdom
Market deep dive · Deadline diary
Covers 2 to 8 October 2026. Consultation dates as at 9 October 2026.
How to read this
↑ Tailwind ↓ Headwind • Neutral
Tailwind helps the businesses affected. Headwind adds cost, delay or risk. Neutral means no clear overall benefit or drawback, though the change may still matter.
Potential means the effect depends on a proposal being adopted or another condition being met. Consultations are proposals open for feedback. They are listed with their closing dates in the diary at the end.
Our six themes
Market Design · Taxes, Subsidies and Public Programmes · Siting, Permitting and Land Use · Grid · Environmental Markets · Supply Chains
The regulatory picture
Updates in this edition, by market and likely effect. Bar length shows how many updates we cover, not how big their impact is. Consultations in the diary are included, and cross-border measures appear in each affected market. Select a market to jump to its section.
↑ Tailwind • Neutral ↓ Headwind
| Across markets | 7 | |||||||||||
| Belgium | 3 | |||||||||||
| Croatia | 2 | |||||||||||
| Czechia | 1 | |||||||||||
| Denmark | 4 | |||||||||||
| Estonia | 1 | |||||||||||
| Finland | 2 | |||||||||||
| France | 3 | |||||||||||
| Greece | 2 | |||||||||||
| Hungary | 1 | |||||||||||
| Ireland | 4 | |||||||||||
| Italy | 4 | |||||||||||
| Lithuania | 1 | |||||||||||
| Netherlands | 3 | |||||||||||
| Norway | 2 | |||||||||||
| Romania | 1 | |||||||||||
| Spain | 1 | |||||||||||
| Sweden | 1 | |||||||||||
| Switzerland | 2 | |||||||||||
| UK | 11 | |||||||||||
This week’s deep dive
🇪🇺 Across markets · Grid
Grid operators start charging for capacity that sits unused
On 7 October, Czechia’s Energy Regulatory Office (ERÚ) and the Czech Energy Association set out two changes to begin charging for reserving grid capacity. The same day, Finland’s Energy Authority announced connection terms that let grid companies take back reserved grid capacity.
A connection contract reserves part of the network for one customer. The operator must keep that part free whether or not the customer uses it, so a reservation that is never used still takes up space on the grid.
In Czechia, customers connected at high and very high voltage will pay for their reserved capacity from 1 January 2027. Previously, they paid nothing for unused capacity, and the cost fell on other customers. Distributors put the gap between these customers’ peak use and their reservations at more than 3 GW, and estimate that up to 15% of the unused capacity could be released straight away. Separately, distributors hold tens of thousands of contracts for future connections that reserve more than 10 GW. Every holder must sign an amendment by early November 2026, or the contract and its reservation lapse. Advance payments for a connection have also become non-refundable deposits, which will be lost if the project is never connected.
In Finland, new standard terms for distribution companies let a grid company shrink a connection under-used for 12 months, and end the contract without refunding the connection fee when agreed construction or commissioning conditions are not met. Companies must offer the terms by 31 January 2027.
These moves will benefit developers with real projects: capacity held by projects that will never be built goes back to the queue, opening up room for other applicants. Batteries are exposed in Finland, where a consultation respondent warned (PDF) that letting grid companies shrink a connection after 12 months of lower-than-agreed use creates an uncontrolled risk for new storage. Czech distributors say manufacturers and electricity producers have asked most about the new tariffs.
What to watch: how many Czech reservations lapse in November, how much capacity is released before January, and the further decrees ERÚ says will move connection costs onto the customers who cause them.
🇪🇺 Across markets
EU-wide and cross-border developments
All-island capacity auctions will require planning consent and a grid offer
5 October · Market Design / Siting, Permitting and Land Use Decision · • Neutral
The Single Electricity Market Committee, which regulates the shared power market of Ireland and Northern Ireland, approved a Capacity Market Code change to add fixed entry criteria. This will require new units bidding into the capacity auctions to show planning permission, or evidence that none is needed, and a grid connection offer or agreement. Demand-side units on exempt industrial land may show their exemption instead. The rule will apply from 1 July 2027. Developers with consented, connected projects will face fewer speculative rivals, while early-stage projects will need to wait for a later auction.
🇧🇪 Belgium
Flanders ends green certificates in every negative-price quarter-hour
7 October · Taxes, Subsidies and Public Programmes / Environmental Markets Order · ↓ Headwind
The Flemish Government amended its energy order so that no green certificates are granted for output in any quarter-hour with a negative electricity price, from 1 January 2027. Until now certificates were withheld only during runs of at least six consecutive negative hours. The rule covers all installations, whatever their start date, and power used on site as well as power exported; plants below 400 kW are exempt (200 kW for plants commissioned from 2026). Green certificates are Flanders’ per-MWh support for solar and wind, so certificate-backed solar loses support in the midday hours when prices turn negative most often.
🇭🇷 Croatia
Croatia publishes its market law, with flexible grid connections
7 October · Grid / Market Design Law · ↑ Tailwind
As of 15 October, the amended Electricity Market Act will require the Croatian Energy Regulatory Agency to write rules for flexible connection agreements. Where the grid is full, a project can connect on limited capacity, with the expected date it becomes firm set in its contract, but without compensation when told to cut output. Aggregators may enter every market, including the balancing market. Holders of energy approvals that stalled because the connection charge was never set see their deadlines start only once it is set.
🇨🇿 Czechia
Czech grid customers will pay for the capacity they reserve
7 October · Grid Announcement · • Neutral
ERÚ confirmed that high-voltage customers will pay for reserved capacity from 1 January 2027, and that unbuilt reservations will lapse unless their holders sign an amendment by early November. For more, see this week’s deep dive.
🇫🇮 Finland
Finnish grid companies can take back unused connection capacity
7 October · Grid Decision · • Neutral
The Energy Authority confirmed new standard connection terms for 73 distribution companies that let a grid company shrink under-used connections and end contracts whose agreed construction or commissioning conditions are not met. For more, see this week’s deep dive.
🇫🇷 France
France adds a Chinese-magnet limit to its onshore wind tender
7 October · Supply Chains / Taxes, Subsidies and Public Programmes Procedure · ↓ Headwind
The Energy Regulatory Commission (CRE) published the rules (PDF) for the 13th round of the onshore wind tender. The round will award support contracts for 1,000 MW; projects will be able to bid from 7 to 17 December. Turbines whose generators use permanent magnets may now source no more than 85% of them from China. A repowered wind farm must also give up its existing support contract to win a new one.
🇬🇷 Greece
Greek transmission users can reclaim grid-extension costs
5 October · Grid Procedure · ↑ Tailwind
The Independent Power Transmission Operator (IPTO) opened the procedure through which users who paid for works extending the transmission grid to their site can recover 50% of the cost, a right granted by a 2022 law that had no working process until now. For a solar, wind, or storage plant connecting at 150 kV or 400 kV, getting half the extension cost back improves returns. IPTO repays in three instalments, the last about 20 months after trial operation ends.
🇭🇺 Hungary
Hungary joins the EU balancing platforms
2 October · Market Design Announcement · ↑ Tailwind
The Hungarian Independent Transmission Operator Company connected the country to Europe’s shared balancing-market platforms on 1 October. These are the Platform for the International Coordination of Automated Frequency Restoration and Stable System Operation, for automatic reserves, and the Manually Activated Reserves Initiative, for manual ones. Hungarian batteries and flexible plants now sell balancing energy against bids from other countries, which widens their market but will likely cause price convergence between national markets.
🇮🇪 Ireland
Ireland’s new planning law starts on 13 October
2 October · Siting, Permitting and Land Use Guidance · • Neutral
The Planning Commission published guidance on what happens to projects already in the planning system when the Planning and Development Act 2024 replaces the old rules on planning permission. For projects that applied before 13 October, the Commission will decide any appeal against it under the old rules, even an appeal it receives after that date. Only applications made from 13 October will go through the new process.
🇮🇹 Italy
Italy publishes the bidding rules for its new renewables auctions
2 October · Taxes, Subsidies and Public Programmes Decree · ↑ Tailwind
The Ministry of the Environment and Energy Security approved the bidding rules (PDF) for the new auctions of its renewable energy sources scheme, known as FER X, which offer price support to solar, wind, and hydro plants above 1 MW. The first auction, in December, seeks 1.5 GW of wind and 350 MW of solar, rising to 2 GW and 3.5 GW if bids come in cheap, plus separate rounds for projects meeting the EU’s Net-Zero Industry Act supply-chain criteria. To enter, a developer must post a guarantee of 5% of a standard build cost. A winner then has 30 days to replace it with a second guarantee worth 10%, which it gets back once the plant is running and loses if it misses its commissioning deadline. When ranking solar bids, the state energy services company (GSE), which runs the auctions, adds a surcharge in zones that have already met their 2030 renewables targets, up to €28.5/MWh in Sardinia and Sicily, though winners still receive their own bid price. Northern solar projects gain a ranking edge. Ties favour, in order, solar repowering on farmland, designated renewable zones, and power purchase agreements of at least 10 years.
🇨🇭 Switzerland
Switzerland adopts wholesale-market abuse rules from 2027
2 October · Market Design Regulation · • Neutral
The Federal Council approved the ordinance on oversight and transparency in wholesale energy markets, which fills in a 2025 law to establish market-abuse and reporting rules like the EU’s. It will take effect on 1 January 2027. Wind, solar, and battery operators that trade electricity in Switzerland, or sell through traders, will face insider-information and reporting duties.
🇬🇧 United Kingdom
Ofgem gives NESO another month for 62 connection offers
2 October · Grid Decision · ↓ Headwind
The Office of Gas and Electricity Markets (Ofgem) agreed to extend NESO’s deadline for about 62 first-phase connection offers under the Gate 2 queue reform, from 30 September to 31 October. National Grid Electricity Transmission was late with its construction offers, and about 25 other offers need more time, mainly at customers’ request. All other dates stand, including 31 January 2027 for second-phase offers. Affected projects will wait a month longer for the terms their financing depends on.
NESO sets the entry rules for its reactive power market
6 October · Market Design / Grid Procedure · ↑ Tailwind
NESO published the qualification rules for its Mid-term Reactive Power Market, which will buy voltage support through tenders up to a year ahead or within the year. Voltage support used to come from large power stations, which are closing. Plants must connect directly to the transmission network and supply reactive power even at 0 MW, so a battery can earn it while idle and still trade energy. Sites in active network management schemes that restrict delivery are excluded. Qualification stays open until the first tender.
Ofgem rejects long self-build code changes and proposes a wider route
7 October · Grid Decision · • Neutral
Ofgem rejected two code changes that would have let transmission customers build connection assets longer than 2 km themselves, because they depended on a companion change withdrawn in June. The same day it proposed letting generation, storage, and demand customers self-build all sole-use assets to the grid, through licence and code changes, citing stakeholder estimates of about 20% lower cost and one to two years saved where no reinforcement is needed. Comments close on 13 November.
Consultation & funding diary
Consultations, calls for evidence and funding rounds in this edition, with closing dates as at 9 October 2026. All items link to their source.
Closing by 16 October
🇫🇷 France ↑ Potential Tailwind
France proposes standard grid-access contracts in island grids🇫🇮 Finland ↓ Potential Headwind
Finland consults on Nuclear Energy Act regulations🇧🇪 Belgium • Neutral
Belgium reviews Elia’s 2027 innovation plan🇱🇹 Lithuania ↑ Tailwind
Litgrid auctions 154 MW of fast frequency response🇷🇴 Romania ↑ Potential Tailwind
Romania sets billing rules for energy communities🇧🇪 Belgium • Neutral
Belgium reviews black-start procurement oversightLooking ahead
21 to 31 October
21 Oct · 🇳🇱 Netherlands • Neutral
Regional grid operators propose 2027 tariffs about 20% higher
22 Oct · 🇪🇸 Spain ↑ Potential Tailwind
Spain plans a 600 MW grid competition at Maciñeira
22 Oct · 🇮🇪 Ireland • Neutral
Ireland begins a review of network tariff structures
22 Oct · 🇩🇰 Denmark ↑ Potential Tailwind
Denmark consults on renewable acceleration areas
23 Oct · 🇩🇰 Denmark • Neutral
Denmark consults on new producer connection charges
24 Oct · 🇳🇱 Netherlands • Neutral
TenneT proposes 2027 tariffs: high-voltage up 20%
26 Oct · 🇭🇷 Croatia • Neutral
Croatia consults on its ten-year distribution grid plan
26 Oct · 🇸🇪 Sweden • Neutral
Svenska kraftnät consults on balancing services from local grids
27 Oct · 🇪🇺 European Union • Neutral
Commission drafts durability rules for industrial batteries
27 Oct · 🇬🇧 United Kingdom • Neutral
UK proposes capacity-market delivery and derating changes
27 Oct · 🇮🇪 Ireland / 🇬🇧 United Kingdom ↑ Potential Tailwind
All-island system-services procurement moves towards market rules
29 Oct · 🇩🇰 Denmark ↓ Potential Headwind
Denmark proposes wider buy-out rights near large solar plants
29 Oct · 🇫🇷 France ↑ Tailwind
France opens a call for greener data-centre equipment
30 Oct · 🇬🇷 Greece • Neutral
Greece consults on renewables-operator fees for self-consumers
30 Oct · 🇮🇹 Italy ↑ Potential Tailwind
Italy consults on aggregated balancing resources
31 Oct · 🇨🇭 Switzerland ↑ Potential Tailwind
Switzerland consults on wind siting plans
3 to 13 November
3 Nov · 🇪🇺 European Union • Neutral
Commission reviews the EU ETS and Market Stability Reserve
6 Nov · 🇬🇧 United Kingdom ↑ Potential Tailwind
Ofgem proposes a register of demand connections
6 Nov · 🇬🇧 United Kingdom ↑ Potential Tailwind
Ofgem proposes minimum standards for connection customers
6 Nov · 🇬🇧 United Kingdom • Neutral
UK seeks evidence on AI in clean energy
9 Nov · 🇮🇹 Italy • Neutral
Italy consults on dispatching on its minor islands
12 Nov · 🇪🇪 Estonia ↑ Potential Tailwind
Estonia consults on a capacity mechanism open to storage
13 Nov · 🇬🇧 United Kingdom ↑ Potential Tailwind
Ofgem proposes self-build of all sole-use transmission assets
13 Nov · 🇪🇺 European Union ↑ Potential Tailwind
EU priority infrastructure: electricity applications
20 to 30 November
20 Nov · 🇳🇴 Norway ↑ Potential Tailwind
Norway proposes faster connection for small solar
30 Nov · 🇩🇰 Denmark ↑ Tailwind
Denmark adds DKK 65 million to business energy grants
December to January
3 Dec · 🇮🇹 Italy • Neutral
Italy seeks companies for an EU nuclear-technology project
4 Dec · 🇪🇺 European Union ↑ Potential Tailwind
EU priority infrastructure: smart-grid applications
8 Dec · 🇮🇪 Ireland ↑ Potential Tailwind
Tonn Nua offshore grid plans open for comment
14 Dec · 🇪🇺 European Union • Neutral
EU consults on data-centre performance standards
16 Dec · 🇳🇱 Netherlands ↑ Tailwind
Netherlands reopens €250 million industrial climate grants
16 Dec · 🇬🇧 United Kingdom • Neutral
Northern Ireland consults on cost-reflective network tariffs
8 Jan 2027 · 🇬🇧 United Kingdom • Neutral
Northern Ireland reviews how generators get firm access
31 Jan 2027 · 🇳🇴 Norway • Neutral
Finnmark wind applications gain three months
Further reading
🇳🇱 Netherlands
Grid congestion progress letter and National Action Programme, autumn 2026 (PDF) · Energy innovation policy letter (PDF)
🇸🇪 Sweden
Reporting of grid build-out in Sweden (Ei R2026:09)
🇬🇧 United Kingdom
Offtaker of Last Resort annual report 2025 to 2026